Yew Huoi, How & Associates | Leading Malaysia Law Firm

MARITIME NEGLIGENCE – PLAINTIFF CLAIMED FOR DAMAGES CAUSED DURING ANCHOR DEPLOYMENT OPERATION – CALDERBANK OFFERS

1. Summary and Facts:

Tom Eastwind 365 Sdn Bhd v Pemunya-Pemunya Kapal atau Vesel Icon Sophia [2025] 9 MLJ 397 the dispute arose when an accident occurred during an anchor deployment operation involving the plaintiff’s accommodation work barge, Two Eastwind and the defendant’s anchor handling tug supply vessel, Icon Sophia at an offshore oilfield. The defendant had been engaged to assist in deploying eight anchors in a predetermined sequence to stabilize the barge under the supervision of the plaintiff’s marine controller. However, the deployment sequence was altered during operation, and the work proceeded despite prevailing sea currents of approximately 1.5 to 2.0 knots.

On the second day of operations, the tug approached the barge to retrieve the final anchor, but due to the strong current, it was unable to maintain a proper approach. After securing the anchor, the tug had trouble maneuvering away and while attempting to pull off using maximum power, its aft section collided with the barge’s hull, causing physical damage. As a result, plaintiff commenced an action in negligence against the defendant.

2. Legal Issues:

  • Whether res ipsa loquitur was applicable under the facts of this case;
  • Whether the court was bound to accept the defendant’s expert’s conclusion; and
  • Whether the plaintiff had established its quantum of damages as claimed.

3. Court’s Findings:

The Court held that the defendant was liable for the damages arising from the incident. However, notwithstanding the plaintiff’s success on the issue of liability, the plaintiff was ordered to bear the costs of the proceedings on the basis that ; –

  • Although, the doctrine of Res Ipsa Loquitur has been established and that the defendant failed to rebut the inference of negligence;
  • However, the court find that the plaintiff has also failed to prove its claims as the evidence submitted was insufficient to support the quantum claimed; and
  • Hence, the plaintiff was penalised in costs due to its unreasonable rejection of Calderbank settlement offers made by defendant and therefore was ordered to bear the costs of RM 80,000 as well as reimburse for the defendant’s expert witness expenses while, the defendant were only ordered to pay RM 50,000 for the nominal damages on the liability.

4. Practical Implications:

This decision marks a significant authority on the application of res ipsa loquitur and damages. Whereas:-

  • The High Court clarified that the doctrine remains applicable even where explanatory evidence is later introduced by the defendant; and
  • It also emphasise that expert evidence is not conclusive and must be grounded in facts; and
  • It highlights the importance of strict proof of damages as failure to substantiate loss can drastically reduce recovery.

The case shows that parties in control of operations may be presumed negligence if an accident occurs, unless they can clearly rebut it with evidence.

If you need more information on our legal updates, our Knowledge and Law News Division at lawnews@yhalaw.com.my would be pleased to assist.

Yew Huoi, How & Associates (Law Firm)
Advocates & Solicitors
No. 1, Jalan Riangria 6
Taman Desa Tiara, Off Jalan Klang Lama
58200 Kuala Lumpur
Tel: +603-7971 3191
Fax: +603-7972 9131
Email: enquiry@yhalaw.com.my
Website: https://yhalaw.com.my


©2026. YEW HUOI, HOW & ASSOCIATES. ALL RIGHTS RESERVED. The contents of this legal updates are intended for general information only and should not be construed as legal advice or legal opinion. If you need further advice or explanation on the subject, please contact our firm. Please do not reproduce, transmit or distribute the contents therein in any form, or by any means as Legal Profession (Publicity) Rules 2001 restrict such circulation.

Note: This material is intended for general information with regard to the practice of YHA. This profile is not intended to create, and does not create a solicitor-client relationship. If you are interested in having YHA to represent you, you must call or visit our office to enable us to discuss the legal matter with you. YHA reserves our right to decline any representation which is in contravention with the Legal Profession Act 1976 and/or the regulations therein.

Recent Post

ADMIRALTY IN REM – WRONGFUL ARREST – POSSESORY RIGHT – ARREST GONE WRONG: WHEN A SHIP ARREST BACKFIRES WITH DAMAGES

In Eletson Holdings Inc & Ors v The Vessel “Paros” [2026] 8 MLJ 80, the High Court set aside an arrest after finding that the plaintiffs had no proprietary or possessory right to the vessel at the time of the writ, as the bareboat charter had already been terminated. The Court held that the claim was in substance a corporate control dispute dressed up as an admiralty action, and emphasised that such disputes do not fall within admiralty jurisdiction. Critically, the plaintiffs’ failure to disclose the termination of the charter when obtaining the arrest warrant amounted to a serious breach, leading the Court to find mala fides or gross negligence and order damages for wrongful arrest. The decision reinforces that ship arrest is a powerful remedy that must be exercised with full disclosure and a proper maritime foundation.

Read More »

GUARANTEE – PERSONAL GUARANTEE ≠ PAY ON DEMAND: COURT DRAWS THE LINE BETWEEN SURETYSHIP AND DEMAND GUARANTEES

In CE Energy DMCC v Bashar [2026] Lloyds’s Rep 267, the Commercial Court clarified that not all guarantees labelled “on demand” will be treated as demand guarantees. On a proper construction, the court held that the personal guarantee in question was a contract of suretyship, requiring proof of the principal debtor’s liability rather than automatic payment upon demand. Crucially, the court found that the debtor’s “irrevocable” admissions of debt in a payment agreement created a binding contractual estoppel, which the guarantor could not challenge. The decision also confirms that, where payment is due on a “day certain”, a seller may still claim the price notwithstanding retention of title. The case underscores the importance of precise drafting and the risks of entering into settlement agreements that conclusively fix liability.

Read More »

MARITIME NEGLIGENCE – PLAINTIFF CLAIMED FOR DAMAGES CAUSED DURING ANCHOR DEPLOYMENT OPERATION – CALDERBANK OFFERS

In Tom Eastwind 365 Sdn Bhd v The Owners of the Vessel “Icon Sophia” [2025] 9 MLJ 397, the High Court held that the doctrine of res ipsa loquitur applied in a maritime collision during an anchor deployment operation, allowing an inference of negligence against the tug owner. The Court clarified that the doctrine is not defeated merely because the defendant adduces evidence explaining the accident – such evidence goes to rebutting the inference, not preventing it. While liability was established due to the tug master’s error of judgment in manoeuvring too close to a stationary barge, the plaintiff failed to properly prove its damages and was awarded only RM50,000. Notably, despite succeeding on liability, the plaintiff was ordered to pay costs after rejecting reasonable Calderbank offers, underscoring the risks of pursuing litigation without properly substantiated claims.

Read More »

JURISDICTION – BILLS OF LADING – BREACH OF HIMALAYA CLAUSE – BREACH OF EXCLUSIVE JURISDICTION CLAUSE – ONEROUS OR UNUSUAL TERMS

In Maersk Guinéa-Bissau SARL v Almar-Hum Bubacar Baldé SARL [2026] 1 Lloyd’s Rep 215, the English Commercial Court held that a shipper was liable for breach of an exclusive jurisdiction clause and a Himalaya clause after commencing proceedings in Guinea-Bissau instead of England. The Court confirmed that such clauses are standard and enforceable, and that commencing foreign proceedings in breach of them can give rise to a claim for damages. Notably, the Court also recognised that Himalaya clauses may be used offensively, allowing subcontractors to recover losses caused by wrongful litigation. The foreign judgment was not recognised due to lack of jurisdiction and denial of natural justice.

Read More »

DELIVERY WITHOUT PRESENTATION OF BILL OF LADING – LOI WON’T SAVE YOU: SHIPOWNER LIABLE FOR MISDELIVERY DESPITE INDEMNITY

In United Overseas Bank Ltd v The “Maersk Katalin” [2026] 1 Lloyd’s Rep 18, the Singapore High Court reaffirmed that delivery of cargo without presentation of original bills of lading remains a fundamental breach, even where carried out against letters of indemnity. The Court held that LOIs merely shift commercial risk but do not authorise misdelivery, and rejected arguments of consent, ratification and causation. Significantly, the Court emphasised that the burden lies on the carrier to prove that the loss would have occurred in any event – a burden not easily discharged. The decision underscores the continued strict liability regime in misdelivery cases, particularly where banks as bill holders are involved.

Read More »

CONTRACT LAW – ‘UK COURTS’ MEANS ENGLAND: COURT UPHOLDS JURISDICTION DESPITE VAGUE CLAUSE

In SMT Global Logistics Ltd v Georgian Airlines LLC [2025] Lloyd’s Rep. Plus 89, the Commercial Court held that a clause referring disputes to “the court in accordance with current legislation of the United Kingdom” was a valid jurisdiction clause in favour of the High Court of England and Wales. The Court also confirmed that the Montreal Convention does not apply to pure contractual claims for non-performance, such as repayment and loss of profits. Emphasising a broad and commercially sensible interpretation, the Court enforced the parties’ choice of forum and refused to stay proceedings, reaffirming that jurisdiction clauses will be upheld unless there are overwhelming reasons to depart.

Read More »
en_USEN