Yew Huoi, How & Associates | Leading Malaysia Law Firm

BREACH OF CONTRACT – COURT OF APPEAL AFFIRMS LAD: CONTRACTOR LIABLE FOR DELAY, EXTRA CLAIMS REJECTED

1. Summary and Facts

In Savelite Engineering Sdn Bhd v Askey Media Technology Sdn Bhd and another appeal [2025] MLJU 2258, Askey Media engaged Savelite to construct a factory in Penang for RM8.6 million, with a completion date of 4 September 2016 and liquidated and ascertained damages (“LAD”) fixed at RM3,300 per day. Practical completion was only certified on 15 September 2017 – a delay of 376 days. The Superintending Officer (“SO”) granted an extension of time (“EOT”) of 143 days, leaving Savelite liable for 233 days of LAD amounting to RM768,900.

Askey Media also claimed loss of rental profits and indemnity payments to its tenant arising from the delay. The High Court allowed the LAD but dismissed the additional claims. Both parties appealed.

2. Legal Issues

• Whether the defendant was estopped from denying that time was of the essence, having accepted the Certificate of Non-Completion (“CNC”) and submitted multiple EOT applications.
• Whether the Plaintiff or Defendant was responsible for the delay.
• Whether time was the essence of the contract.
• Whether the quantum of damages was proportionate and reasonable.

3. Court’s Findings

• The court dismissed both appeals from the plaintiff and defendant.
• The delay was attributable to the Defendant, as time was of the essence in the contract, and the slow progress of works resulted in the delay.
• The Court varied the High Court’s order by imposing 5% interest per annum on the liquidated damages award, effective from 26.1.2017 until full settlement, pursuant to its discretion, as provided for under the contract.
• Equitable estoppel did not apply as the contract expressly stipulated that time was of the essence, and the completion deadline was clear.

4. Practical Implications

This decision affirms several important legal principles governing the contract including:
• The liquidated damages clauses are generally enforceable, provided they are genuine pre-estimate of loss and not a penalty.
• The burden lies upon the contractor to establish that a delay is excusable, as failure to do so renders the contractor liable for liquidated damages.
• The contract must be properly drafted for liquidated damages clauses as it will put the developers or employers a strong legal protection in the event of delay.

Recent Post

MONEYLENDING – ILLEGALITY– COURT OF APPEAL: LICENSED MONEYLENDERS CAN RECOVER VOID LOANS UNDER RESTITUTION

In Golden Wheel Credit Sdn Bhd v Dato’ Siah Teong Din [2025] MLJU 2245, the Court of Appeal ruled that a licensed moneylender may recover loan monies under section 66 of the Contracts Act 1950, even when the moneylending agreements are void for technical non-compliance with the Moneylenders Act 1951. The Court held that while the agreements were void and unenforceable, they were not illegal, as the lender was duly licensed and the transactions were genuine. Applying the Federal Court’s Detik Ria principles, the Court found that restitution was proportionate and justified, ordering repayment of RM3.38 million to prevent unjust enrichment.

Read More »

TRADEMARKS ACT 1976 – INFRINGEMENT OF TRADEMARK AND/OR TORT OF PASSING OFF – LEXUS VS LEX: FEDERAL COURT REAFFIRMS EXCLUSIVE TRADEMARK RIGHTS FOR MUNCHY’S

In Munchy Food Industries Sdn Bhd v Huasin Food Industries Sdn Bhd [2022] 1 MLJ 377, the Federal Court restored the High Court’s decision in favour of Munchy’s, ruling that Huasin’s LEX biscuits infringed and passed off the LEXUS trademark. The Court held that “honest concurrent use” cannot be raised where the defendant’s mark is unregistered and unpleaded, and that a trademark owner need not vary its registered mark before commencing infringement or passing off actions. The decision strengthens protection for registered proprietors and highlights that pleadings and exclusivity remain central in trademark disputes.

Read More »

BREACH OF CONTRACT – COURT OF APPEAL AFFIRMS LAD: CONTRACTOR LIABLE FOR DELAY, EXTRA CLAIMS REJECTED

In Savelite Engineering Sdn Bhd v Askey Media Technology Sdn Bhd [2025] CLJU 1808, the Court of Appeal upheld the employer’s entitlement to RM768,900 in liquidated damages (LAD) for a 233-day delay in completing a factory project. The Court held that time was of the essence, and the contractor was estopped from denying liability after applying for extensions of time. Applying section 75 of the Contracts Act 1950 and Cubic Electronics, the LAD was found proportionate (~9% of the contract price) and thus reasonable compensation. Claims for additional losses, such as lost rental profits and indemnity to tenants, were barred where an LAD clause exists.

Read More »

MARITIME LAW – SOYBEANS, SALVAGE SALES AND SUIT RIGHTS: COURT CLARIFIES CARGO DAMAGE RECOVERY

In AMS Ameropa Marketing and Sales AG & Anor v Ocean Unity Navigation Inc (The “Doric Valour”) 1 Lloyd’s Rep 389, the UK Commercial Court awarded US$293,755.10 for heat-damaged soybeans shipped from Louisiana to Egypt. Although only 70 – 80 mt of beans were physically damaged, 3,600 mt were reasonably treated as distressed and sold in a salvage sale at an 18% discount. The Court held that the assignee of the cargo receiver had valid title to sue, and that the salvage sale was a reasonable act of mitigation. Ancillary claims for warehousing, survey, and transport costs failed for lack of proof.

Read More »

SHIPPING – ADMIRALTY – FLOATING CASINOS AS COLLATERAL: COURT HOLDS GAMING EQUIPMENT FALLS WITHIN SHIP MORTGAGE

In KfW IPEX-Bank GmbH v Owner of the Vessel “World Dream” [2025] 2 Lloyd’s Rep 137, the Singapore High Court ruled that casino gaming equipment on board a luxury cruise ship formed part of the mortgaged vessel. The Court held that under long-standing admiralty principles, “ship” covers not only navigation gear but also items necessary for the vessel’s commercial adventure. As the World Dream was designed as a floating resort with gaming as a central attraction, the slot machines and casino tables were integral to its purpose and thus subject to the mortgage. The decision highlights the wide scope of ship mortgages and the importance of expressly addressing high-value movable assets in financing documents.

Read More »
en_USEN
× Contact Us