Yew Huoi, How & Associates | Leading Malaysia Law Firm

EMPLOYMENT – TERMINATION TANGLES: WHEN PERFORMANCE REVIEWS PRECEDE CONTRACT ENDINGS

ILLUSTRATIVE SCENARIO

X and Y entered into an agreement where X appointed Y to assist with a delivery service in Selangor. The agreement included a review procedure (Clause 8) for X to follow if Y’s performance was deemed unsatisfactory.

A few months later, X alleged multiple breaches of contract by Y and issued a termination notice giving 30 days’ notice under Clause 7. However, X’s letter did not specify any reason for the termination.

Clause 7 – Termination X shall be entitled to terminate this agreement by giving thirty (30) days notice to Y if Y is unable to provide satisfactory services as provided under the agreement.

Clause 8 – Performance Review 8.1 In the event that X shall determine Y’s performance of its obligations under this Agreement as unsatisfactory, Y shall be given thirty (30) days to remedy the unsatisfactory situation.

8.2 If X finds the unsatisfactory situation is not remedied at the end of thirty (30) days given under Clause 8.1, X shall have the option of treating such unsatisfactory performance as an event of default which entitles X to terminate this Agreement pursuant to Clause 7 and accordingly X shall be entitled to all reliefs provided under Clause 7.

KEY ISSUES

The issue is whether X can unilaterally terminate the contract under Clause 7 without specifying reasons in the termination notice?

LEGAL PRINCIPLES

  • There are two possible interpretations of Clauses 7 and 8:
    1. Clause 7 can only be invoked after the procedure in Clause 8 is completed, requiring a notice with specific reasons.
    2. Clause 8 does not need to be invoked before Clause 7, as Clause 7 does not explicitly require reasons in the termination notice.
  • Case law suggests that a termination notice is not always invalid if reasons are not provided. However, if the contract includes a ‘grace period’ for the defaulting party to remedy its performance, the non-defaulting party may be required to communicate reasons for termination.
  • Clause 8’s review procedure is not unilateral and aims to protect both parties’ interests, ensuring that unsatisfactory situations are remedied and Y can avoid breach and termination.
  • Therefore, interpreting Clause 8 as a mandatory precursor to Clause 7 makes more commercial sense. X should have initiated a review and provided specific reasons before terminating the contract.

APPLICATION TO SCENARIO

X was obligated to initiate a performance review under Clause 8 before terminating the contract and to provide specific reasons for termination. The failure to do so likely makes the termination notice invalid.

REFERENCE CASE

  • SPM Membrane Switch Sdn. Bhd. v. Kerajaan Negeri Selangor [2016] 1 MLJ 464

Recent Post

WHEN CARGO GOES ASTRAY: THE RISKS OF DELIVERING WITHOUT A BILL OF LADING

A recent High Court ruling involved a plaintiff who suffered severe brain damage after an emergency caesarean section at 33 weeks of pregnancy due to alleged medical negligence. The court examined whether the medical team breached their duty of care by failing to properly monitor the patient, resulting in oxygen deprivation and irreversible damage. The defendants, including doctors and nurses, were found liable for not acting on clear warning signs, leading to significant damages awarded to the plaintiff for her physical and mental disabilities.

Read More »

TORT — NEGLIGENCE — MEDICAL NEGLIGENCE — A MISSED LIFELINE: COURT HOLDS MEDICAL TEAM LIABLE FOR BRAIN DAMAGE IN HIGH-RISK PREGNANCY CASE

A recent High Court ruling involved a plaintiff who suffered severe brain damage after an emergency caesarean section at 33 weeks of pregnancy due to alleged medical negligence. The court examined whether the medical team breached their duty of care by failing to properly monitor the patient, resulting in oxygen deprivation and irreversible damage. The defendants, including doctors and nurses, were found liable for not acting on clear warning signs, leading to significant damages awarded to the plaintiff for her physical and mental disabilities.

Read More »

NAVIGATING LIABILITY: THE UNSEAWORTHINESS OF THE FJORD WIND AND ITS LEGAL CONSEQUENCES

The Court of Appeal ruled in The Fjord Wind case that the vessel was unseaworthy at the time of departure from Rosario on 30.06.1990, due to known issues with the crankpin bearings that had not been adequately addressed. This unseaworthiness led to a main engine failure shortly after departure, necessitating the transhipment of cargo and incurring additional costs.

The court found the shipowners liable for damages, emphasizing their failure to exercise due diligence in maintaining the vessel’s seaworthiness. The ruling underscores the critical importance of thorough inspections and repairs in maritime operations, highlighting the legal responsibilities of shipowners to prevent unseaworthiness and related liabilities.

Read More »

STRATA MANAGEMENT – COMMON PROPERTY CONUNDRUM: CENTRALIZED AC COSTS AND THE STRATA MANAGEMENT DEBATE

In a recent legal dispute, the classification of centralized air conditioning facilities (CACF) as common property has come under scrutiny. The Plaintiff, a parcel owner in Tower A of Menara UOA Bangsar, challenged the Management Body’s use of maintenance funds for the upkeep of CACF, which primarily benefits parcels in Tower B. The court is likely to dismiss the Plaintiff’s claim, reinforcing the principle that as long as CACF serves two or more occupiers, it is deemed common property, thus falling under the Management Body’s purview without requiring reimbursement from individual parcel owners.

Read More »
en_USEN
× Contact Us