Yew Huoi, How & Associates | Leading Malaysia Law Firm

LIMITATION OF ACTION – TIME WAITS FOR NO CLAIM – COURT OF APPEAL STRIKES OUT PKA’S LATE ACTION

1. Summary and Facts

In Kuala Dimensi Sdn Bhd v Port Kelang Authority [2025] 2 MLJ 238, the appeal arose from an application by Kuala Dimensi Sdn Bhd (“KDSB”) to strike out a claim filed by Port Kelang Authority (“PKA”) on grounds of limitation. PKA had brought a suit against KDSB for alleged breaches relating to agreements involving the development and sale of land. KDSB contended that PKA’s claim was time-barred, having been filed beyond the prescribed statutory limitation period. PKA argued that its claim was filed within the applicable limitation period, asserting that it had discovered the breaches only at a later date, thus invoking principles relating to the postponement of limitation periods. The High Court initially dismissed KDSB’s application to strike out PKA’s claim, prompting KDSB to appeal.

2. Legal Issues

• Whether PKA’s claims against KDSB were statute-barred under the Limitation Act 1953.
• Whether the postponement of limitation under section 29 of the Limitation Act 1953 applied, considering PKA’s contention of late discovery of the breaches.
• Whether the High Court erred in dismissing KDSB’s striking-out application on limitation grounds.

3. Court’s Findings

• The Court of Appeal allowed KDSB’s appeal, reversing the High Court’s decision and ordering the striking out of PKA’s claim.
• The claims brought by PKA were statute-barred, having exceeded the six-year limitation period under section 6 of the Limitation Act 1953.
• The court held that section 29 (postponement of limitation) of the Limitation Act did not apply, as PKA failed to establish that it could not have discovered the alleged breaches earlier with reasonable diligence.
• The Court found that PKA had knowledge or ought reasonably to have had knowledge of the breaches earlier, and thus could not rely on the postponement of limitation. Consequently, the action was time-barred.

4. Practical Implications

This judgment provides clarity on limitation periods in civil claims and highlights the following implications:
• Parties must be vigilant in monitoring contractual obligations and assert claims promptly upon breach to avoid limitation issues.
• Claimants seeking to invoke section 29 (postponement of limitation) must demonstrate conclusively that they could not have reasonably discovered the breaches earlier.
• The decision reinforces the courts’ strict interpretation of limitation statutes, highlighting the necessity for claimants to act swiftly and diligently upon discovery or suspicion of contractual breaches.

Recent Post

CIVIL PROCEDURE – STRIKE OUT UNDER ORDER 18 RULE 19(1)(A),(B) RULES OF COURT 2012 – EXTENSION OF TIME APPLICATION

In Badan Pengurusan Subang Parkhomes v Zen Estates Sdn Bhd [2025] MLJU 3591, the High Court reaffirmed that non-compliance with Order 37 Rule 1(5) of the Rules of Court 2012 does not automatically invalidate assessment of damages proceedings. The Court held that procedural rules must be read with the overriding objective of ensuring justice, and that the six-month time limit to file a Notice of Appointment is directory, not mandatory. Finding no prejudice to the defendant and noting active case management by the plaintiff, the Court dismissed the developer’s strike-out bid and allowed an extension of time for assessment to proceed. The decision underscores the judiciary’s commitment to substantive fairness over procedural rigidity in post-judgment proceedings.

Read More »

TORT – PURE ECONOMIC LOSS BAR REAFFIRMED: MMC LIABLE FOR NEGLIGENCE BUT PROTECTED FROM LOST PROFIT CLAIMS

In Asia Pacific Higher Learning Sdn Bhd v Majlis Perubatan Malaysia & Anor [2025] MLJU 3144, the High Court awarded over RM2 million in damages against the Malaysian Medical Council (MMC) for negligence, breach of statutory duty, and misfeasance during its accreditation of Lincoln University College’s medical programmes. While the court allowed direct financial losses such as survey costs, it barred claims exceeding RM550 million for lost profits, reaffirming the Federal Court’s rulings in Steven Phoa and UDA Holdings that pure economic loss is not recoverable from public or statutory bodies. The second defendant was further ordered to pay RM100,000 in exemplary damages for acting with targeted malice, marking a rare personal liability finding against a regulatory officer.

Read More »

ERINFORD INJUNCTION – COURT OF APPEAL CLARIFIES: EX-PARTE ERINFORD INJUNCTIONS ARE THE EXCEPTION, NOT THE RULE

In Edisijuta Parking Sdn Bhd v TH Universal Builders Sdn Bhd & Anor [2025] 5 MLJ 524, the Court of Appeal clarified that ex parte Erinford injunctions at the appellate stage should only be granted in truly exceptional circumstances where giving notice would defeat the purpose of the order. Wong Kian Kheong JCA held that, under rule 50 of the Rules of the Court of Appeal 1994, such applications should generally be heard inter partes to ensure fairness and prevent abuse. Exercising powers under section 44(1) of the Courts of Judicature Act 1964, the Court granted a conditional interim Erinford injunction pending appeal, fortified by a RM200,000 deposit and an undertaking to pay damages. The ruling provides clear guidance on balancing urgency, procedural fairness, and judicial efficiency in appellate injunctions.

Read More »

TOTAL FAILURE CONSIDERATION – FEDERAL COURT OVERRULES BERJAYA TIMES SQUARE: TOTAL FAILURE OF CONSIDERATION REDEFINED

In Lim Swee Choo & Anor v Ong Koh Hou @ Won Kok Fong [2025] 6 MLJ 327, the Federal Court unanimously overruled Berjaya Times Square Sdn Bhd v M Concept Sdn Bhd and clarified that the doctrine of total failure of consideration applies only to restitutionary relief, not to contractual termination. The Court held that the correct test is whether the promisor has performed any part of the contractual duties in respect of which payment is due, adopting Stocznia Gdanska SA v Latvian Shipping Co [1998] 1 WLR 574. Finding that the appellants had partly performed their obligations and the respondent had derived benefits, the Court rejected the respondent’s claim for restitution and restored the appellants’ contractual claim. The landmark decision restores clarity between contract and restitution, reinforcing commercial certainty in Malaysian law.

Read More »

CONTRACT (BILL OF LADING) – NO DUTY TO DETECT FRAUD: COURT CLEARS MAERSK OF LIABILITY FOR FALSE CONTAINER WEIGHTS

In Stournaras Stylianos Monoprosopi EPE v Maersk A/S [2025] 2 Lloyd’s Rep 323, the English Commercial Court held that carriers are not liable for fraudulent misdeclarations by shippers where bills of lading are issued for sealed containers. The Court ruled that Maersk had no duty to verify or cross-check declared weights against Verified Gross Mass (VGM) data under the SOLAS Convention, as its obligation under the Hague Rules extended only to the apparent external condition of cargo. However, the judgment signals that a limited duty of care could arise in future where a carrier is put on notice of fraud. For now, carriers may rely on shipper declarations, but consignees must exercise commercial vigilance and due diligence when relying on bills for payment.

Read More »

EXEMPLARY DAMAGES – STATUTORY BODY DUTY – DAMAGES – OBTAINING APPROVAL

In Big Man Management Sdn Bhd v Tenaga Nasional Bhd [2025] 5 MLJ 290, the Federal Court reinstated nearly RM3.56 million in special damages and awarded RM100,000 in exemplary damages against TNB for wrongfully disconnecting electricity to an ice factory. The Court ruled that “strict proof” of special damages does not mean a higher burden beyond the civil standard of proof and affirmed that TNB, as a statutory monopoly, breached its statutory duty by using disconnection as leverage to collect payment. The judgment underscores that public utilities cannot misuse statutory powers, and consumers wrongfully deprived of essential services may be entitled to punitive remedies in exceptional cases.

Read More »
en_USEN
× Contact Us