CIVIL PROCEDURE – STRIKE OUT UNDER ORDER 18 RULE 19(1)(A),(B) RULES OF COURT 2012 – EXTENSION OF TIME APPLICATION

1. Summary and Facts:
Badan Pengurusan Subang Parkhomes V Zen Estates Sdn Bhd (Sebelum ini dikenali sebagai Sendi Bangga Development Sdn Bhd) (Fadhullah & Assoc Consulting Engineers Sdn Bhd, Pihak ketiga)” [2025] MLJU 3591 the dispute arose from a claim by the management body of a condominium, Badan Pengurusan Subang Parkhomes (“the Plaintiff”), against the developer, Zen Estates Sdn Bhd (“the Defendant”), for latent defects in the building. The High Court had earlier, on 22 January 2024, found the defendant liable for the defects and ordered damages to be assessed, including damages for unrectified defects, non-compliance with the Electricity Regulations 1994, and loss of use of common property. The defendant, in turn, had a third-party claim against its engineering consultant, Fadhullah & Associates Consulting Engineers Sdn Bhd, for indemnity relating to the electrical non-compliance. Following the judgment on liability, the matter proceeded to assessment of damages, during which procedural disputes arose between the parties.

2. Legal Issues:
• Whether the plaintiff’s delay in filing the Notice of Appointment for Assessment of Damages beyond six months under Order 37 rule 1(5) of the Rules of Court 2012 should cause the assessment proceedings to be struck out.
• Whether the defendant suffered any actual prejudice due to the plaintiff’s delay in filing the Notice of Appointment.

3. Court’s Findings:
• The High Court dismissed the Defendant’s application and allowed the plaintiff’s request for an extension.
• The court found that the Defendant had failed to substantiate any actual prejudice or damages suffered from the delay.
• Order 37 Rule 1(5) ROC 2012 was not mandatory, citing the Court of appeal decision in Vellasamy
a/l Ponnusamy & Ors v Gurbachan Singh a/l Bagawan Singh & Anor [2020] MLJU 695, which emphasized that;
• The Rules of Court 2012 adopt an inquisitorial approach and case management approach rather than a rigid adversarial one.

4. Practical Implications:
This judgment affirms that Malaysian courts emphasize on this substantive justice over procedural technicalities, whereas:
• The court characterized the defendat’s application with costs of RM5,000.00 as a mere afterthought aimed at delaying the assessment of damages.
• Order 37 ROC 2012 should not be interpreted rigidly and non-compliance willl not render proceedings void unless it causes substantial prejudice or contravenes an “unless order”.
This case reinforces the judiciary’s commitment to the overriding objective of ensuring matters are resolved on their merits rather than being struck out for technical delay.

Sorotan Terkini

CIVIL PROCEDURE – STRIKE OUT UNDER ORDER 18 RULE 19(1)(A),(B) RULES OF COURT 2012 – EXTENSION OF TIME APPLICATION

In Badan Pengurusan Subang Parkhomes v Zen Estates Sdn Bhd [2025] MLJU 3591, the High Court reaffirmed that non-compliance with Order 37 Rule 1(5) of the Rules of Court 2012 does not automatically invalidate assessment of damages proceedings. The Court held that procedural rules must be read with the overriding objective of ensuring justice, and that the six-month time limit to file a Notice of Appointment is directory, not mandatory. Finding no prejudice to the defendant and noting active case management by the plaintiff, the Court dismissed the developer’s strike-out bid and allowed an extension of time for assessment to proceed. The decision underscores the judiciary’s commitment to substantive fairness over procedural rigidity in post-judgment proceedings.

Read More »

TORT – PURE ECONOMIC LOSS BAR REAFFIRMED: MMC LIABLE FOR NEGLIGENCE BUT PROTECTED FROM LOST PROFIT CLAIMS

In Asia Pacific Higher Learning Sdn Bhd v Majlis Perubatan Malaysia & Anor [2025] MLJU 3144, the High Court awarded over RM2 million in damages against the Malaysian Medical Council (MMC) for negligence, breach of statutory duty, and misfeasance during its accreditation of Lincoln University College’s medical programmes. While the court allowed direct financial losses such as survey costs, it barred claims exceeding RM550 million for lost profits, reaffirming the Federal Court’s rulings in Steven Phoa and UDA Holdings that pure economic loss is not recoverable from public or statutory bodies. The second defendant was further ordered to pay RM100,000 in exemplary damages for acting with targeted malice, marking a rare personal liability finding against a regulatory officer.

Read More »

ERINFORD INJUNCTION – COURT OF APPEAL CLARIFIES: EX-PARTE ERINFORD INJUNCTIONS ARE THE EXCEPTION, NOT THE RULE

In Edisijuta Parking Sdn Bhd v TH Universal Builders Sdn Bhd & Anor [2025] 5 MLJ 524, the Court of Appeal clarified that ex parte Erinford injunctions at the appellate stage should only be granted in truly exceptional circumstances where giving notice would defeat the purpose of the order. Wong Kian Kheong JCA held that, under rule 50 of the Rules of the Court of Appeal 1994, such applications should generally be heard inter partes to ensure fairness and prevent abuse. Exercising powers under section 44(1) of the Courts of Judicature Act 1964, the Court granted a conditional interim Erinford injunction pending appeal, fortified by a RM200,000 deposit and an undertaking to pay damages. The ruling provides clear guidance on balancing urgency, procedural fairness, and judicial efficiency in appellate injunctions.

Read More »

TOTAL FAILURE CONSIDERATION – FEDERAL COURT OVERRULES BERJAYA TIMES SQUARE: TOTAL FAILURE OF CONSIDERATION REDEFINED

In Lim Swee Choo & Anor v Ong Koh Hou @ Won Kok Fong [2025] 6 MLJ 327, the Federal Court unanimously overruled Berjaya Times Square Sdn Bhd v M Concept Sdn Bhd and clarified that the doctrine of total failure of consideration applies only to restitutionary relief, not to contractual termination. The Court held that the correct test is whether the promisor has performed any part of the contractual duties in respect of which payment is due, adopting Stocznia Gdanska SA v Latvian Shipping Co [1998] 1 WLR 574. Finding that the appellants had partly performed their obligations and the respondent had derived benefits, the Court rejected the respondent’s claim for restitution and restored the appellants’ contractual claim. The landmark decision restores clarity between contract and restitution, reinforcing commercial certainty in Malaysian law.

Read More »

CONTRACT (BILL OF LADING) – NO DUTY TO DETECT FRAUD: COURT CLEARS MAERSK OF LIABILITY FOR FALSE CONTAINER WEIGHTS

In Stournaras Stylianos Monoprosopi EPE v Maersk A/S [2025] 2 Lloyd’s Rep 323, the English Commercial Court held that carriers are not liable for fraudulent misdeclarations by shippers where bills of lading are issued for sealed containers. The Court ruled that Maersk had no duty to verify or cross-check declared weights against Verified Gross Mass (VGM) data under the SOLAS Convention, as its obligation under the Hague Rules extended only to the apparent external condition of cargo. However, the judgment signals that a limited duty of care could arise in future where a carrier is put on notice of fraud. For now, carriers may rely on shipper declarations, but consignees must exercise commercial vigilance and due diligence when relying on bills for payment.

Read More »

EXEMPLARY DAMAGES – STATUTORY BODY DUTY – DAMAGES – OBTAINING APPROVAL

In Big Man Management Sdn Bhd v Tenaga Nasional Bhd [2025] 5 MLJ 290, the Federal Court reinstated nearly RM3.56 million in special damages and awarded RM100,000 in exemplary damages against TNB for wrongfully disconnecting electricity to an ice factory. The Court ruled that “strict proof” of special damages does not mean a higher burden beyond the civil standard of proof and affirmed that TNB, as a statutory monopoly, breached its statutory duty by using disconnection as leverage to collect payment. The judgment underscores that public utilities cannot misuse statutory powers, and consumers wrongfully deprived of essential services may be entitled to punitive remedies in exceptional cases.

Read More »