BREACH OF CONTRACT – COURT OF APPEAL AFFIRMS LAD: CONTRACTOR LIABLE FOR DELAY, EXTRA CLAIMS REJECTED
In Savelite Engineering Sdn Bhd v Askey Media Technology Sdn Bhd [2025] CLJU 1808, the Court of Appeal upheld the employer’s entitlement to RM768,900 in liquidated damages (LAD) for a 233-day delay in completing a factory project. The Court held that time was of the essence, and the contractor was estopped from denying liability after applying for extensions of time. Applying section 75 of the Contracts Act 1950 and Cubic Electronics, the LAD was found proportionate (~9% of the contract price) and thus reasonable compensation. Claims for additional losses, such as lost rental profits and indemnity to tenants, were barred where an LAD clause exists.