Yew Huoi, How & Associates | Leading Malaysia Law Firm

BREACH OF CONTRACT – COURT FINDS EDGENTA IN BREACH: SUPPLYING USED LINENS NOT GOOD ENOUGH FOR UKM HOSPITAL

1. Summary and Facts

In Universiti Kebangsaan Malaysia v Edgenta Facilities Management Sdn Bhd [2025] 11 MLJ 783, UKM entered a laundry services contract with Edgenta for PPUKM, requiring Edgenta to maintain a “five par” linen level – laundry service contract. UKM claimed Edgenta failed to supply new linens and imposed penalties of RM3,996,344.47 based on missing items, price per item, and days delayed. Edgenta argued the contract did not specify “new” linens, supplied a mix of linens, disputed the penalty formula, and alleged UKM increased linen requirements without notice, counterclaiming RM3.64 million for wrongful deductions.

2. Legal Issues

• Whether the defendant was contractually obligated to supply new linens rather than used or recycled linens.
• Whether the defendant’s counterclaim for allegedly wrongful deductions had any basis or merit.
• Whether the plaintiff’s penalty calculation method and amount were valid.

3. Court’s Findings

• The High Court allowed UKM’s claim for RM3,996,344.47 with interest at 5% per annum from the date of filing until full settlement and dismissed Edgenta’s counterclaim with costs.
• It was held that when a dispute arises from a contract, the entire contract must be interpreted considering its factual background, commercial purpose, and business nature to determine the parties’ intention using an objective approach.
• Although the contract did not expressly include the word “new,” the Court found that both parties intended and understood that only new linens were required.
• The Court admitted extrinsic evidence under proviso (b) to section 92 of the Evidence Act 1950, holding that parol evidence was admissible to clarify a contractual silence where it was not inconsistent with the written terms.
• Key documents, including meeting minutes and correspondence, showed that the defendant had repeatedly acknowledged its obligation to supply “new linens” and sought extensions of time to meet this requirement.
• The penalty formula was valid, as the phrase “until the five par requirements is fulfilled” clearly included a time element.
• The counterclaims by the Defendant lacked evidence and appeared tactical after receiving the Plaintiff’s penalty demand.

4. Practical Implications

This decision affirms several important legal principles including:
• Even if a contract is silent, courts may infer intent from surrounding evidence and commercial sense.
• Parol evidence rule allows clarification of silent terms (s 92(b) Evidence Act 1950).
• Penalty clauses are enforceable if they serve a legitimate commercial purpose and are reasonable.

Recent Post

CIVIL PROCEDURE – STRIKE OUT UNDER ORDER 18 RULE 19(1)(A),(B) RULES OF COURT 2012 – EXTENSION OF TIME APPLICATION

In Badan Pengurusan Subang Parkhomes v Zen Estates Sdn Bhd [2025] MLJU 3591, the High Court reaffirmed that non-compliance with Order 37 Rule 1(5) of the Rules of Court 2012 does not automatically invalidate assessment of damages proceedings. The Court held that procedural rules must be read with the overriding objective of ensuring justice, and that the six-month time limit to file a Notice of Appointment is directory, not mandatory. Finding no prejudice to the defendant and noting active case management by the plaintiff, the Court dismissed the developer’s strike-out bid and allowed an extension of time for assessment to proceed. The decision underscores the judiciary’s commitment to substantive fairness over procedural rigidity in post-judgment proceedings.

Read More »

TORT – PURE ECONOMIC LOSS BAR REAFFIRMED: MMC LIABLE FOR NEGLIGENCE BUT PROTECTED FROM LOST PROFIT CLAIMS

In Asia Pacific Higher Learning Sdn Bhd v Majlis Perubatan Malaysia & Anor [2025] MLJU 3144, the High Court awarded over RM2 million in damages against the Malaysian Medical Council (MMC) for negligence, breach of statutory duty, and misfeasance during its accreditation of Lincoln University College’s medical programmes. While the court allowed direct financial losses such as survey costs, it barred claims exceeding RM550 million for lost profits, reaffirming the Federal Court’s rulings in Steven Phoa and UDA Holdings that pure economic loss is not recoverable from public or statutory bodies. The second defendant was further ordered to pay RM100,000 in exemplary damages for acting with targeted malice, marking a rare personal liability finding against a regulatory officer.

Read More »

ERINFORD INJUNCTION – COURT OF APPEAL CLARIFIES: EX-PARTE ERINFORD INJUNCTIONS ARE THE EXCEPTION, NOT THE RULE

In Edisijuta Parking Sdn Bhd v TH Universal Builders Sdn Bhd & Anor [2025] 5 MLJ 524, the Court of Appeal clarified that ex parte Erinford injunctions at the appellate stage should only be granted in truly exceptional circumstances where giving notice would defeat the purpose of the order. Wong Kian Kheong JCA held that, under rule 50 of the Rules of the Court of Appeal 1994, such applications should generally be heard inter partes to ensure fairness and prevent abuse. Exercising powers under section 44(1) of the Courts of Judicature Act 1964, the Court granted a conditional interim Erinford injunction pending appeal, fortified by a RM200,000 deposit and an undertaking to pay damages. The ruling provides clear guidance on balancing urgency, procedural fairness, and judicial efficiency in appellate injunctions.

Read More »

TOTAL FAILURE CONSIDERATION – FEDERAL COURT OVERRULES BERJAYA TIMES SQUARE: TOTAL FAILURE OF CONSIDERATION REDEFINED

In Lim Swee Choo & Anor v Ong Koh Hou @ Won Kok Fong [2025] 6 MLJ 327, the Federal Court unanimously overruled Berjaya Times Square Sdn Bhd v M Concept Sdn Bhd and clarified that the doctrine of total failure of consideration applies only to restitutionary relief, not to contractual termination. The Court held that the correct test is whether the promisor has performed any part of the contractual duties in respect of which payment is due, adopting Stocznia Gdanska SA v Latvian Shipping Co [1998] 1 WLR 574. Finding that the appellants had partly performed their obligations and the respondent had derived benefits, the Court rejected the respondent’s claim for restitution and restored the appellants’ contractual claim. The landmark decision restores clarity between contract and restitution, reinforcing commercial certainty in Malaysian law.

Read More »

CONTRACT (BILL OF LADING) – NO DUTY TO DETECT FRAUD: COURT CLEARS MAERSK OF LIABILITY FOR FALSE CONTAINER WEIGHTS

In Stournaras Stylianos Monoprosopi EPE v Maersk A/S [2025] 2 Lloyd’s Rep 323, the English Commercial Court held that carriers are not liable for fraudulent misdeclarations by shippers where bills of lading are issued for sealed containers. The Court ruled that Maersk had no duty to verify or cross-check declared weights against Verified Gross Mass (VGM) data under the SOLAS Convention, as its obligation under the Hague Rules extended only to the apparent external condition of cargo. However, the judgment signals that a limited duty of care could arise in future where a carrier is put on notice of fraud. For now, carriers may rely on shipper declarations, but consignees must exercise commercial vigilance and due diligence when relying on bills for payment.

Read More »

EXEMPLARY DAMAGES – STATUTORY BODY DUTY – DAMAGES – OBTAINING APPROVAL

In Big Man Management Sdn Bhd v Tenaga Nasional Bhd [2025] 5 MLJ 290, the Federal Court reinstated nearly RM3.56 million in special damages and awarded RM100,000 in exemplary damages against TNB for wrongfully disconnecting electricity to an ice factory. The Court ruled that “strict proof” of special damages does not mean a higher burden beyond the civil standard of proof and affirmed that TNB, as a statutory monopoly, breached its statutory duty by using disconnection as leverage to collect payment. The judgment underscores that public utilities cannot misuse statutory powers, and consumers wrongfully deprived of essential services may be entitled to punitive remedies in exceptional cases.

Read More »
zh_TWZH
× 联系我们