Yew Huoi, How & Associates | Leading Malaysia Law Firm

COLLISION COURSE – COURT WEIGHS ANCHOR DRAGGING AND LIABILITY AT SEA

Summary and Facts

The case The Kiran Australia v Belpareil [2024] 2 Lloyd’s Rep 323 examines a collision between two vessels, the Kiran Australia and Belpareil. The collision resulted from Belpareil’s anchor dragging, which led to a loss of control over its movements and ultimately a collision with Kiran Australia. The court evaluated each party’s liability, apportioning fault based on the actions and omissions of each vessel.

Key Issues

  1. Negligence Due to Dragging Anchor: Was Belpareil negligent because its anchor dragged?
  2. Timely Warnings and Response: Did Belpareil fail to issue timely warnings and respond adequately?
  3. Apportionment of Fault: Should fault be weighted in favor of Kiran Australia despite its limited evasive actions?

Court’s Findings

  • The court found Belpareil primarily at fault for failing to rebut the presumption of negligence associated with dragging anchor. Maritime law often presumes negligence when a vessel’s anchor drags unless unavoidable circumstances can be demonstrated, which Belpareil could not establish.
  • Belpareil also failed to meet its duty to issue prompt warnings to Kiran Australia or to seek tug assistance quickly. These delays substantially contributed to the collision and affected the court’s apportionment of liability.
  • Although Kiran Australia did attempt evasive action, its limited response was hampered by Belpareil’s delays and lack of communication. The court assigned 70% of the fault to Belpareil and 30% to Kiran Australia, placing greater responsibility on the vessel that failed to manage the potential hazard.
  • Kiran Australia was apportioned 30% of the fault because it had a duty to take reasonable evasive action. Despite its attempts to avoid the collision, the court found that these measures were insufficient.

Practical Implications

  • This case highlights the stringent standards of vigilance and communication expected to prevent maritime collisions.
  • Vessel operators should prioritize actively monitoring anchor stability, especially in challenging weather or currents, as failure to do so can result in a presumption of negligence and increased liability.
  • The ruling underscores the need for timely communication with nearby vessels and immediate action, such as engaging tug assistance when needed.
  • Vessel owners must ensure clear protocols for managing anchor dragging and train crews to prioritize swift communication in emergency situations.

Conclusion

This case underscores vessels’ responsibilities in managing anchor dragging risks and highlights the critical role of timely communication to minimize collision risks.

Recent Post

CIVIL PROCEDURE – STRIKE OUT UNDER ORDER 18 RULE 19(1)(A),(B) RULES OF COURT 2012 – EXTENSION OF TIME APPLICATION

In Badan Pengurusan Subang Parkhomes v Zen Estates Sdn Bhd [2025] MLJU 3591, the High Court reaffirmed that non-compliance with Order 37 Rule 1(5) of the Rules of Court 2012 does not automatically invalidate assessment of damages proceedings. The Court held that procedural rules must be read with the overriding objective of ensuring justice, and that the six-month time limit to file a Notice of Appointment is directory, not mandatory. Finding no prejudice to the defendant and noting active case management by the plaintiff, the Court dismissed the developer’s strike-out bid and allowed an extension of time for assessment to proceed. The decision underscores the judiciary’s commitment to substantive fairness over procedural rigidity in post-judgment proceedings.

Read More »

TORT – PURE ECONOMIC LOSS BAR REAFFIRMED: MMC LIABLE FOR NEGLIGENCE BUT PROTECTED FROM LOST PROFIT CLAIMS

In Asia Pacific Higher Learning Sdn Bhd v Majlis Perubatan Malaysia & Anor [2025] MLJU 3144, the High Court awarded over RM2 million in damages against the Malaysian Medical Council (MMC) for negligence, breach of statutory duty, and misfeasance during its accreditation of Lincoln University College’s medical programmes. While the court allowed direct financial losses such as survey costs, it barred claims exceeding RM550 million for lost profits, reaffirming the Federal Court’s rulings in Steven Phoa and UDA Holdings that pure economic loss is not recoverable from public or statutory bodies. The second defendant was further ordered to pay RM100,000 in exemplary damages for acting with targeted malice, marking a rare personal liability finding against a regulatory officer.

Read More »

ERINFORD INJUNCTION – COURT OF APPEAL CLARIFIES: EX-PARTE ERINFORD INJUNCTIONS ARE THE EXCEPTION, NOT THE RULE

In Edisijuta Parking Sdn Bhd v TH Universal Builders Sdn Bhd & Anor [2025] 5 MLJ 524, the Court of Appeal clarified that ex parte Erinford injunctions at the appellate stage should only be granted in truly exceptional circumstances where giving notice would defeat the purpose of the order. Wong Kian Kheong JCA held that, under rule 50 of the Rules of the Court of Appeal 1994, such applications should generally be heard inter partes to ensure fairness and prevent abuse. Exercising powers under section 44(1) of the Courts of Judicature Act 1964, the Court granted a conditional interim Erinford injunction pending appeal, fortified by a RM200,000 deposit and an undertaking to pay damages. The ruling provides clear guidance on balancing urgency, procedural fairness, and judicial efficiency in appellate injunctions.

Read More »

TOTAL FAILURE CONSIDERATION – FEDERAL COURT OVERRULES BERJAYA TIMES SQUARE: TOTAL FAILURE OF CONSIDERATION REDEFINED

In Lim Swee Choo & Anor v Ong Koh Hou @ Won Kok Fong [2025] 6 MLJ 327, the Federal Court unanimously overruled Berjaya Times Square Sdn Bhd v M Concept Sdn Bhd and clarified that the doctrine of total failure of consideration applies only to restitutionary relief, not to contractual termination. The Court held that the correct test is whether the promisor has performed any part of the contractual duties in respect of which payment is due, adopting Stocznia Gdanska SA v Latvian Shipping Co [1998] 1 WLR 574. Finding that the appellants had partly performed their obligations and the respondent had derived benefits, the Court rejected the respondent’s claim for restitution and restored the appellants’ contractual claim. The landmark decision restores clarity between contract and restitution, reinforcing commercial certainty in Malaysian law.

Read More »

CONTRACT (BILL OF LADING) – NO DUTY TO DETECT FRAUD: COURT CLEARS MAERSK OF LIABILITY FOR FALSE CONTAINER WEIGHTS

In Stournaras Stylianos Monoprosopi EPE v Maersk A/S [2025] 2 Lloyd’s Rep 323, the English Commercial Court held that carriers are not liable for fraudulent misdeclarations by shippers where bills of lading are issued for sealed containers. The Court ruled that Maersk had no duty to verify or cross-check declared weights against Verified Gross Mass (VGM) data under the SOLAS Convention, as its obligation under the Hague Rules extended only to the apparent external condition of cargo. However, the judgment signals that a limited duty of care could arise in future where a carrier is put on notice of fraud. For now, carriers may rely on shipper declarations, but consignees must exercise commercial vigilance and due diligence when relying on bills for payment.

Read More »

EXEMPLARY DAMAGES – STATUTORY BODY DUTY – DAMAGES – OBTAINING APPROVAL

In Big Man Management Sdn Bhd v Tenaga Nasional Bhd [2025] 5 MLJ 290, the Federal Court reinstated nearly RM3.56 million in special damages and awarded RM100,000 in exemplary damages against TNB for wrongfully disconnecting electricity to an ice factory. The Court ruled that “strict proof” of special damages does not mean a higher burden beyond the civil standard of proof and affirmed that TNB, as a statutory monopoly, breached its statutory duty by using disconnection as leverage to collect payment. The judgment underscores that public utilities cannot misuse statutory powers, and consumers wrongfully deprived of essential services may be entitled to punitive remedies in exceptional cases.

Read More »
zh_TWZH
× 联系我们