Yew Huoi, How & Associates | Leading Malaysia Law Firm

法律资讯

法律资讯

Filter by Category
合約法

TOTAL FAILURE CONSIDERATION – FEDERAL COURT OVERRULES BERJAYA TIMES SQUARE: TOTAL FAILURE OF CONSIDERATION REDEFINED

In Lim Swee Choo & Anor v Ong Koh Hou @ Won Kok Fong [2025] 6 MLJ 327, the Federal Court unanimously overruled Berjaya Times Square Sdn Bhd v M Concept Sdn Bhd and clarified that the doctrine of total failure of consideration applies only to restitutionary relief, not to contractual termination. The Court held that the correct test is whether the promisor has performed any part of the contractual duties in respect of which payment is due, adopting Stocznia Gdanska SA v Latvian Shipping Co [1998] 1 WLR 574. Finding that the appellants had partly performed their obligations and the respondent had derived benefits, the Court rejected the respondent’s claim for restitution and restored the appellants’ contractual claim. The landmark decision restores clarity between contract and restitution, reinforcing commercial certainty in Malaysian law.

Read More »
侵權行為

EXEMPLARY DAMAGES – STATUTORY BODY DUTY – DAMAGES – OBTAINING APPROVAL

In Big Man Management Sdn Bhd v Tenaga Nasional Bhd [2025] 5 MLJ 290, the Federal Court reinstated nearly RM3.56 million in special damages and awarded RM100,000 in exemplary damages against TNB for wrongfully disconnecting electricity to an ice factory. The Court ruled that “strict proof” of special damages does not mean a higher burden beyond the civil standard of proof and affirmed that TNB, as a statutory monopoly, breached its statutory duty by using disconnection as leverage to collect payment. The judgment underscores that public utilities cannot misuse statutory powers, and consumers wrongfully deprived of essential services may be entitled to punitive remedies in exceptional cases.

Read More »
合約法

BREACH OF CONTRACT – COURT FINDS EDGENTA IN BREACH: SUPPLYING USED LINENS NOT GOOD ENOUGH FOR UKM HOSPITAL

In Universiti Kebangsaan Malaysia v Edgenta Facilities Management Sdn Bhd [2025] 11 MLJ 783, the High Court held that Edgenta breached its laundry services contract with UKM by failing to supply new linens as intended under the agreement. Although the contract did not explicitly use the word “new,” the Court admitted extrinsic evidence under section 92(b) of the Evidence Act 1950 to establish both parties’ common understanding. The Court also upheld UKM’s RM3.99 million penalty as valid and proportionate, finding that the formula including “days delayed” was consistent with the contract and served a legitimate commercial purpose. Edgenta’s counterclaim for wrongful deductions was dismissed for lack of proof.

Read More »
合約法

MONEYLENDING – ILLEGALITY– COURT OF APPEAL: LICENSED MONEYLENDERS CAN RECOVER VOID LOANS UNDER RESTITUTION

In Golden Wheel Credit Sdn Bhd v Dato’ Siah Teong Din [2025] MLJU 2245, the Court of Appeal ruled that a licensed moneylender may recover loan monies under section 66 of the Contracts Act 1950, even when the moneylending agreements are void for technical non-compliance with the Moneylenders Act 1951. The Court held that while the agreements were void and unenforceable, they were not illegal, as the lender was duly licensed and the transactions were genuine. Applying the Federal Court’s Detik Ria principles, the Court found that restitution was proportionate and justified, ordering repayment of RM3.38 million to prevent unjust enrichment.

Read More »
合約法

BREACH OF CONTRACT – COURT OF APPEAL AFFIRMS LAD: CONTRACTOR LIABLE FOR DELAY, EXTRA CLAIMS REJECTED

In Savelite Engineering Sdn Bhd v Askey Media Technology Sdn Bhd [2025] CLJU 1808, the Court of Appeal upheld the employer’s entitlement to RM768,900 in liquidated damages (LAD) for a 233-day delay in completing a factory project. The Court held that time was of the essence, and the contractor was estopped from denying liability after applying for extensions of time. Applying section 75 of the Contracts Act 1950 and Cubic Electronics, the LAD was found proportionate (~9% of the contract price) and thus reasonable compensation. Claims for additional losses, such as lost rental profits and indemnity to tenants, were barred where an LAD clause exists.

Read More »
合約法

MONEYLENDERS ACT 1951- UNJUST ENRICHMENT OR ILLEGAL LOAN? COURT WEIGHS RESTITUTION AGAINST THE MONEYLENDERS ACT

In Golden Wheel Credit Sdn Bhd v Dato’ Siah Teong Din [2021] 12 MLJ, the Court considered whether a licensed moneylender, whose loan agreements were void for non-compliance with the Moneylenders Act 1951, could nevertheless pursue restitutionary remedies. The plaintiff, having advanced RM3.5 million which was channelled to the defendant’s company, sought recovery on grounds of money had and received and unjust enrichment under the Contracts Act 1950. The defendant applied to strike out the claim, arguing that it was merely an indirect attempt to enforce an illegal loan. The case illustrates the delicate balance between statutory illegality under the Moneylenders Act and the equitable principles underpinning restitution.

Read More »
更新

LIMITATION OF ACTION – TIME WAITS FOR NO CLAIM – COURT OF APPEAL STRIKES OUT PKA’S LATE ACTION

In the notable decision of Kuala Dimensi Sdn Bhd v Port Kelang Authority [2025] 2 MLJ 238, the Court of Appeal firmly emphasized the critical importance of timely action in contractual disputes, ruling that PKA’s claims against KDSB were statute-barred under the Limitation Act 1953. The Court decisively clarified that parties cannot invoke the postponement of limitation periods without demonstrating genuine inability to discover breaches earlier through reasonable diligence. This judgment serves as a stern reminder to litigants to vigilantly monitor their contractual rights and act promptly to avoid losing claims due to statutory time limitations.

Read More »
仲裁法

ARBITRATION – SHIPPING – REPAIR GONE WRONG: CLARIFYING SHIPYARD LIABILITY IN ARBITRATION (“MARE NOVA”)

In Hai v Pai & Anor [2025] 8 MLJ 211, the Court decisively addressed the delicate intersection of marital betrayal and financial fairness. Affirming the award of damages against a third-party “homewrecker,” the decision underscores the judiciary’s firm stance on compensating emotional and financial harm arising from adultery. Furthermore, the ruling clarifies the importance of precise documentation and the consequences of commingling inherited wealth, reinforcing that matrimonial asset division requires careful, individualized assessment to achieve true equity.

Read More »
更新

BREACH OF CONTRACT – FORCE MAJEURE – FORCE MAJEURE UNPACKED: WHEN ‘REASONABLE ENDEAVOURS’ DON’T BEND CONTRACT TERMS

The UK Supreme Court clarified the limits of force majeure clauses, ruling that “reasonable endeavours” do not require a party to accept alternative performance outside the agreed contract terms. This decision emphasizes that force majeure clauses are meant to uphold, not alter, original obligations – even in unexpected circumstances. The case serves as a reminder for businesses to define alternative options explicitly within their contracts if flexibility is desired.

Read More »
合約法

CONTRACTS – CONTRACT FOR THE SALE OF GOODS FOB – REMOTENESS OF DAMAGES IN BACK-TO-BACK CONTRACTS – COURT DEFINES LIMITS ON LIABILITY

In a complex dispute involving back-to-back contracts, the court clarified the boundaries for assessing damages, emphasizing that a chain of contracts does not automatically ensure liability passes through. Although substantial losses resulted from delays and disruption, the court highlighted the importance of the remoteness of damages, noting that each contract’s unique terms ultimately limited liability. This decision emphasise the need for parties in chain contracts to carefully define indemnity and liability provisions, as damages are assessed based on foreseeability rather than simply the structure of linked agreements.

Read More »

Categories

Recent Legal Updates

CIVIL PROCEDURE – STRIKE OUT UNDER ORDER 18 RULE 19(1)(A),(B) RULES OF COURT 2012 – EXTENSION OF TIME APPLICATION

In Badan Pengurusan Subang Parkhomes v Zen Estates Sdn Bhd [2025] MLJU 3591, the High Court reaffirmed that non-compliance with Order 37 Rule 1(5) of the Rules of Court 2012 does not automatically invalidate assessment of damages proceedings. The Court held that procedural rules must be read with the overriding objective of ensuring justice, and that the six-month time limit to file a Notice of Appointment is directory, not mandatory. Finding no prejudice to the defendant and noting active case management by the plaintiff, the Court dismissed the developer’s strike-out bid and allowed an extension of time for assessment to proceed. The decision underscores the judiciary’s commitment to substantive fairness over procedural rigidity in post-judgment proceedings.

Read More »

TORT – PURE ECONOMIC LOSS BAR REAFFIRMED: MMC LIABLE FOR NEGLIGENCE BUT PROTECTED FROM LOST PROFIT CLAIMS

In Asia Pacific Higher Learning Sdn Bhd v Majlis Perubatan Malaysia & Anor [2025] MLJU 3144, the High Court awarded over RM2 million in damages against the Malaysian Medical Council (MMC) for negligence, breach of statutory duty, and misfeasance during its accreditation of Lincoln University College’s medical programmes. While the court allowed direct financial losses such as survey costs, it barred claims exceeding RM550 million for lost profits, reaffirming the Federal Court’s rulings in Steven Phoa and UDA Holdings that pure economic loss is not recoverable from public or statutory bodies. The second defendant was further ordered to pay RM100,000 in exemplary damages for acting with targeted malice, marking a rare personal liability finding against a regulatory officer.

Read More »

ERINFORD INJUNCTION – COURT OF APPEAL CLARIFIES: EX-PARTE ERINFORD INJUNCTIONS ARE THE EXCEPTION, NOT THE RULE

In Edisijuta Parking Sdn Bhd v TH Universal Builders Sdn Bhd & Anor [2025] 5 MLJ 524, the Court of Appeal clarified that ex parte Erinford injunctions at the appellate stage should only be granted in truly exceptional circumstances where giving notice would defeat the purpose of the order. Wong Kian Kheong JCA held that, under rule 50 of the Rules of the Court of Appeal 1994, such applications should generally be heard inter partes to ensure fairness and prevent abuse. Exercising powers under section 44(1) of the Courts of Judicature Act 1964, the Court granted a conditional interim Erinford injunction pending appeal, fortified by a RM200,000 deposit and an undertaking to pay damages. The ruling provides clear guidance on balancing urgency, procedural fairness, and judicial efficiency in appellate injunctions.

Read More »

TOTAL FAILURE CONSIDERATION – FEDERAL COURT OVERRULES BERJAYA TIMES SQUARE: TOTAL FAILURE OF CONSIDERATION REDEFINED

In Lim Swee Choo & Anor v Ong Koh Hou @ Won Kok Fong [2025] 6 MLJ 327, the Federal Court unanimously overruled Berjaya Times Square Sdn Bhd v M Concept Sdn Bhd and clarified that the doctrine of total failure of consideration applies only to restitutionary relief, not to contractual termination. The Court held that the correct test is whether the promisor has performed any part of the contractual duties in respect of which payment is due, adopting Stocznia Gdanska SA v Latvian Shipping Co [1998] 1 WLR 574. Finding that the appellants had partly performed their obligations and the respondent had derived benefits, the Court rejected the respondent’s claim for restitution and restored the appellants’ contractual claim. The landmark decision restores clarity between contract and restitution, reinforcing commercial certainty in Malaysian law.

Read More »

CONTRACT (BILL OF LADING) – NO DUTY TO DETECT FRAUD: COURT CLEARS MAERSK OF LIABILITY FOR FALSE CONTAINER WEIGHTS

In Stournaras Stylianos Monoprosopi EPE v Maersk A/S [2025] 2 Lloyd’s Rep 323, the English Commercial Court held that carriers are not liable for fraudulent misdeclarations by shippers where bills of lading are issued for sealed containers. The Court ruled that Maersk had no duty to verify or cross-check declared weights against Verified Gross Mass (VGM) data under the SOLAS Convention, as its obligation under the Hague Rules extended only to the apparent external condition of cargo. However, the judgment signals that a limited duty of care could arise in future where a carrier is put on notice of fraud. For now, carriers may rely on shipper declarations, but consignees must exercise commercial vigilance and due diligence when relying on bills for payment.

Read More »

EXEMPLARY DAMAGES – STATUTORY BODY DUTY – DAMAGES – OBTAINING APPROVAL

In Big Man Management Sdn Bhd v Tenaga Nasional Bhd [2025] 5 MLJ 290, the Federal Court reinstated nearly RM3.56 million in special damages and awarded RM100,000 in exemplary damages against TNB for wrongfully disconnecting electricity to an ice factory. The Court ruled that “strict proof” of special damages does not mean a higher burden beyond the civil standard of proof and affirmed that TNB, as a statutory monopoly, breached its statutory duty by using disconnection as leverage to collect payment. The judgment underscores that public utilities cannot misuse statutory powers, and consumers wrongfully deprived of essential services may be entitled to punitive remedies in exceptional cases.

Read More »

Categories

zh_TWZH
× 联系我们