Yew Huoi, How & Associates | Leading Malaysia Law Firm

SHIP SALE – LOSING THE DEAL, LOSING THE DAMAGES? THE LILA LISBON CASE AND THE LIMITS OF MARKET LOSS RECOVERY

1. Summary and Facts:

The case The Lila Lisbon [2025] 1 Lloyd’s Rep 101, Orion Shipping and Trading Ltd (“OSAT”) agreed to sell the Capesize bulk carrier Lila Lisbon to Great Asia Maritime Ltd (“GAM”) under a Memorandum of Agreement (MOA) based on the Norwegian Saleform 2012. The delivery deadline was extended multiple times, but OSAT failed to deliver by the final deadline on 15.10.2021. GAM terminated the agreement and sought damages, claiming the difference between the contract price and the vessel’s market price at termination. The tribunal awarded GAM USD1.85 million in damages under Clause 14 of the MOA. OSAT appealed, arguing that such damages were only recoverable in a case of repudiatory breach.

2. Legal issues:

i. Whether a buyer, who lawfully cancels a sale contract under Clause 14 due to the seller’s “proven negligence” in failing to deliver by the cancellation date, is entitled to recover loss of bargain damages in the absence of a repudiatory breach?

3. Court Findings:

• The court ruled in favor of OSAT, setting aside the tribunal’s award of loss of bargain damages.
• There was no positive contractual obligation on OSAT to tender notice of readiness by the cancelling date, only a right for the buyer to cancel if delivery was not made.
• Clause 14B of the MOA did not automatically entitle the buyer to loss of bargain damages unless the seller was in repudiatory breach.
• The failure to deliver did not amount to non-delivery under Section 51 of the Sale of Goods Act 1979, as the cancellation right in Clause 14 was a discretionary buyer’s right rather than a seller’s obligation.
• The case was distinguishable from traditional sale of goods disputes where non-delivery gives rise to market loss damages.

4. Practical Implications:

• Buyers relying on a contract’s default clause to recover market loss damages must ensure the clause expressly provides for such a remedy.
• The judgment clarifies that cancellation under an MOA’s default clause does not necessarily equate to repudiatory breach or entitle a buyer to market damages.
• Sellers can benefit from contractual language that limits liability, while buyers should ensure that compensation clauses clearly cover market loss.
• In a rising market, buyers must assess whether waiting to establish a repudiatory breach is necessary before terminating, as a wrongful termination could have legal and financial repercussions.

Recent Post

CIVIL PROCEDURE – STRIKE OUT UNDER ORDER 18 RULE 19(1)(A),(B) RULES OF COURT 2012 – EXTENSION OF TIME APPLICATION

In Badan Pengurusan Subang Parkhomes v Zen Estates Sdn Bhd [2025] MLJU 3591, the High Court reaffirmed that non-compliance with Order 37 Rule 1(5) of the Rules of Court 2012 does not automatically invalidate assessment of damages proceedings. The Court held that procedural rules must be read with the overriding objective of ensuring justice, and that the six-month time limit to file a Notice of Appointment is directory, not mandatory. Finding no prejudice to the defendant and noting active case management by the plaintiff, the Court dismissed the developer’s strike-out bid and allowed an extension of time for assessment to proceed. The decision underscores the judiciary’s commitment to substantive fairness over procedural rigidity in post-judgment proceedings.

Read More »

TORT – PURE ECONOMIC LOSS BAR REAFFIRMED: MMC LIABLE FOR NEGLIGENCE BUT PROTECTED FROM LOST PROFIT CLAIMS

In Asia Pacific Higher Learning Sdn Bhd v Majlis Perubatan Malaysia & Anor [2025] MLJU 3144, the High Court awarded over RM2 million in damages against the Malaysian Medical Council (MMC) for negligence, breach of statutory duty, and misfeasance during its accreditation of Lincoln University College’s medical programmes. While the court allowed direct financial losses such as survey costs, it barred claims exceeding RM550 million for lost profits, reaffirming the Federal Court’s rulings in Steven Phoa and UDA Holdings that pure economic loss is not recoverable from public or statutory bodies. The second defendant was further ordered to pay RM100,000 in exemplary damages for acting with targeted malice, marking a rare personal liability finding against a regulatory officer.

Read More »

ERINFORD INJUNCTION – COURT OF APPEAL CLARIFIES: EX-PARTE ERINFORD INJUNCTIONS ARE THE EXCEPTION, NOT THE RULE

In Edisijuta Parking Sdn Bhd v TH Universal Builders Sdn Bhd & Anor [2025] 5 MLJ 524, the Court of Appeal clarified that ex parte Erinford injunctions at the appellate stage should only be granted in truly exceptional circumstances where giving notice would defeat the purpose of the order. Wong Kian Kheong JCA held that, under rule 50 of the Rules of the Court of Appeal 1994, such applications should generally be heard inter partes to ensure fairness and prevent abuse. Exercising powers under section 44(1) of the Courts of Judicature Act 1964, the Court granted a conditional interim Erinford injunction pending appeal, fortified by a RM200,000 deposit and an undertaking to pay damages. The ruling provides clear guidance on balancing urgency, procedural fairness, and judicial efficiency in appellate injunctions.

Read More »

TOTAL FAILURE CONSIDERATION – FEDERAL COURT OVERRULES BERJAYA TIMES SQUARE: TOTAL FAILURE OF CONSIDERATION REDEFINED

In Lim Swee Choo & Anor v Ong Koh Hou @ Won Kok Fong [2025] 6 MLJ 327, the Federal Court unanimously overruled Berjaya Times Square Sdn Bhd v M Concept Sdn Bhd and clarified that the doctrine of total failure of consideration applies only to restitutionary relief, not to contractual termination. The Court held that the correct test is whether the promisor has performed any part of the contractual duties in respect of which payment is due, adopting Stocznia Gdanska SA v Latvian Shipping Co [1998] 1 WLR 574. Finding that the appellants had partly performed their obligations and the respondent had derived benefits, the Court rejected the respondent’s claim for restitution and restored the appellants’ contractual claim. The landmark decision restores clarity between contract and restitution, reinforcing commercial certainty in Malaysian law.

Read More »

CONTRACT (BILL OF LADING) – NO DUTY TO DETECT FRAUD: COURT CLEARS MAERSK OF LIABILITY FOR FALSE CONTAINER WEIGHTS

In Stournaras Stylianos Monoprosopi EPE v Maersk A/S [2025] 2 Lloyd’s Rep 323, the English Commercial Court held that carriers are not liable for fraudulent misdeclarations by shippers where bills of lading are issued for sealed containers. The Court ruled that Maersk had no duty to verify or cross-check declared weights against Verified Gross Mass (VGM) data under the SOLAS Convention, as its obligation under the Hague Rules extended only to the apparent external condition of cargo. However, the judgment signals that a limited duty of care could arise in future where a carrier is put on notice of fraud. For now, carriers may rely on shipper declarations, but consignees must exercise commercial vigilance and due diligence when relying on bills for payment.

Read More »

EXEMPLARY DAMAGES – STATUTORY BODY DUTY – DAMAGES – OBTAINING APPROVAL

In Big Man Management Sdn Bhd v Tenaga Nasional Bhd [2025] 5 MLJ 290, the Federal Court reinstated nearly RM3.56 million in special damages and awarded RM100,000 in exemplary damages against TNB for wrongfully disconnecting electricity to an ice factory. The Court ruled that “strict proof” of special damages does not mean a higher burden beyond the civil standard of proof and affirmed that TNB, as a statutory monopoly, breached its statutory duty by using disconnection as leverage to collect payment. The judgment underscores that public utilities cannot misuse statutory powers, and consumers wrongfully deprived of essential services may be entitled to punitive remedies in exceptional cases.

Read More »
en_USEN
× Contact Us