Yew Huoi, How & Associates | Leading Malaysia Law Firm

EMPLOYMENT – TERMINATION TANGLES: WHEN PERFORMANCE REVIEWS PRECEDE CONTRACT ENDINGS

ILLUSTRATIVE SCENARIO

X and Y entered into an agreement where X appointed Y to assist with a delivery service in Selangor. The agreement included a review procedure (Clause 8) for X to follow if Y’s performance was deemed unsatisfactory.

A few months later, X alleged multiple breaches of contract by Y and issued a termination notice giving 30 days’ notice under Clause 7. However, X’s letter did not specify any reason for the termination.

Clause 7 – Termination X shall be entitled to terminate this agreement by giving thirty (30) days notice to Y if Y is unable to provide satisfactory services as provided under the agreement.

Clause 8 – Performance Review 8.1 In the event that X shall determine Y’s performance of its obligations under this Agreement as unsatisfactory, Y shall be given thirty (30) days to remedy the unsatisfactory situation.

8.2 If X finds the unsatisfactory situation is not remedied at the end of thirty (30) days given under Clause 8.1, X shall have the option of treating such unsatisfactory performance as an event of default which entitles X to terminate this Agreement pursuant to Clause 7 and accordingly X shall be entitled to all reliefs provided under Clause 7.

KEY ISSUES

The issue is whether X can unilaterally terminate the contract under Clause 7 without specifying reasons in the termination notice?

LEGAL PRINCIPLES

  • There are two possible interpretations of Clauses 7 and 8:
    1. Clause 7 can only be invoked after the procedure in Clause 8 is completed, requiring a notice with specific reasons.
    2. Clause 8 does not need to be invoked before Clause 7, as Clause 7 does not explicitly require reasons in the termination notice.
  • Case law suggests that a termination notice is not always invalid if reasons are not provided. However, if the contract includes a ‘grace period’ for the defaulting party to remedy its performance, the non-defaulting party may be required to communicate reasons for termination.
  • Clause 8’s review procedure is not unilateral and aims to protect both parties’ interests, ensuring that unsatisfactory situations are remedied and Y can avoid breach and termination.
  • Therefore, interpreting Clause 8 as a mandatory precursor to Clause 7 makes more commercial sense. X should have initiated a review and provided specific reasons before terminating the contract.

APPLICATION TO SCENARIO

X was obligated to initiate a performance review under Clause 8 before terminating the contract and to provide specific reasons for termination. The failure to do so likely makes the termination notice invalid.

REFERENCE CASE

  • SPM Membrane Switch Sdn. Bhd. v. Kerajaan Negeri Selangor [2016] 1 MLJ 464

Recent Post

JURISDICTION – CHOOSING THE RIGHT COURT: THE SEA JUSTICE CASE HIGHLIGHTS WHERE MARITIME DISPUTES SHOULD BE HEARD

In The Sea Justice cases [2024] 2 Lloyd’s Rep 383 and [2024] 2 Lloyd’s Rep 429, the Singapore courts tackled a key question: which country should handle a maritime dispute when incidents span international waters? After examining the location of the collision, existing limitation funds in China, and witness availability, the courts concluded that China was the more appropriate forum. This ruling highlights that courts will often defer to the jurisdiction with the closest ties to the incident, ensuring efficient and fair handling of cross-border maritime disputes. This approach is also relevant in Malaysia, where similar principles apply.

Read More »

BREACH OF CONTRACT – FORCE MAJEURE – FORCE MAJEURE UNPACKED: WHEN ‘REASONABLE ENDEAVOURS’ DON’T BEND CONTRACT TERMS

The UK Supreme Court clarified the limits of force majeure clauses, ruling that “reasonable endeavours” do not require a party to accept alternative performance outside the agreed contract terms. This decision emphasizes that force majeure clauses are meant to uphold, not alter, original obligations – even in unexpected circumstances. The case serves as a reminder for businesses to define alternative options explicitly within their contracts if flexibility is desired.

Read More »

NEGLIGENCE – MEDICAL NEGLIGENCE – HOSPITAL ACCOUNTABILITY REINFORCED: COURT UPHOLDS NON-DELEGABLE DUTY IN MEDICAL NEGLIGENCE

In a landmark ruling, the court reinforced the hospital’s non-delegable duty of care, holding that even when services are outsourced to independent contractors, the hospital remains accountable for patient welfare. This decision emphasizes that vulnerable patients, reliant on medical institutions, must be safeguarded against harm caused by third-party providers. The ruling ultimately rejected the hospital’s defense of independence for contracted consultants, underscoring a high standard of duty owed to patients.

Read More »

CONTRACTS – CONTRACT FOR THE SALE OF GOODS FOB – REMOTENESS OF DAMAGES IN BACK-TO-BACK CONTRACTS – COURT DEFINES LIMITS ON LIABILITY

In a complex dispute involving back-to-back contracts, the court clarified the boundaries for assessing damages, emphasizing that a chain of contracts does not automatically ensure liability passes through. Although substantial losses resulted from delays and disruption, the court highlighted the importance of the remoteness of damages, noting that each contract’s unique terms ultimately limited liability. This decision emphasise the need for parties in chain contracts to carefully define indemnity and liability provisions, as damages are assessed based on foreseeability rather than simply the structure of linked agreements.

Read More »

TORT – BREAKING CONFIDENTIALITY – COURT CRACKS DOWN ON INSIDER LEAKS AND CORPORATE CONSPIRACY

In a recent ruling on corporate confidentiality, the court held two former employees liable for disclosing sensitive business information to a competitor, deeming it a breach of both employment contracts and fiduciary duties. This case highlights the serious consequences of unauthorized sharing of proprietary data and reinforces that such disclosures can lead to substantial legal and financial repercussions, even for the receiving parties if they knowingly benefit from confidential information.

Read More »
zh_TWZH
× 联系我们