Yew Huoi, How & Associates | Leading Malaysia Law Firm

CONTRACT – SALE AND PURCHASE OF PROPERTY – DELIVERY OF VACANT POSSESSION

John signed a sale and purchase agreement (“SPA“) with developer Y in the year 2012 to purchase properties in the later housing plan. The SPA, on the other hand, followed the one established in schedule H of the Housing Development (Control and Licensing) Regulations 1989 (“the HDR“) with one exception: instead of 36 months, the SPA specified 54 months for vacant possession of the properties to be given to the plaintiffs. The Minister had apparently approved the EOT for 54 months in 2010. The delivery of vacant possession of their respective properties to John was in January 2017. In the ruling in Ang Ming Lee, John sued developer Y, claiming that the controller’s extension of time (“EOT”) was unlawful and that the parties were obligated to use the mandated SPA laid forth in schedule H, which only allows for a 36-month completion term. 

Q: Does the developer have the power to deviate from the terms prescribed in the statutory contract of sale in Schedule H of the HDR? 

A: Yes, back then Ang Ming Lee had not been decided. As a result, the only method for a developer to get an EOT was to hand up vacant possession and stray from the Schedule H requirements. The notion that the defendant was wrong to deviate from the terms only comes in the year 2020. 

Q: Can John argue that he has no knowledge of the extension of time? 

A: No, the reason behind this was if Developer Y obtained an extension of time before John signed the SPA. This shows that John has knowledge of the extension of time obtained by developer Y before the project begins. 

Q: Can John raise an argument in the validity of the extension of time? 

A: Yes, because the EOT is a Ministry of Housing and Local Government decision, it can only be contested through a judicial review and a writ action.

Q: Is it possible for John to file a claim for LAD before the limitation period expires?

A: It depends on when did John file a claim for LAD against developer Y for late delivery of vacant possession. This is because the cause of action accrues on the date of the SPA and not when vacant possession was delivered.

This legal updates were made based on the recent decision of the court in Chin Kok Woo & Ors v Sky Park Properties Sdn Bhd & Ors [2022] 10 MLJ 153. 

Recent Post

JURISDICTION – CHOOSING THE RIGHT COURT: THE SEA JUSTICE CASE HIGHLIGHTS WHERE MARITIME DISPUTES SHOULD BE HEARD

In The Sea Justice cases [2024] 2 Lloyd’s Rep 383 and [2024] 2 Lloyd’s Rep 429, the Singapore courts tackled a key question: which country should handle a maritime dispute when incidents span international waters? After examining the location of the collision, existing limitation funds in China, and witness availability, the courts concluded that China was the more appropriate forum. This ruling highlights that courts will often defer to the jurisdiction with the closest ties to the incident, ensuring efficient and fair handling of cross-border maritime disputes. This approach is also relevant in Malaysia, where similar principles apply.

Read More »

BREACH OF CONTRACT – FORCE MAJEURE – FORCE MAJEURE UNPACKED: WHEN ‘REASONABLE ENDEAVOURS’ DON’T BEND CONTRACT TERMS

The UK Supreme Court clarified the limits of force majeure clauses, ruling that “reasonable endeavours” do not require a party to accept alternative performance outside the agreed contract terms. This decision emphasizes that force majeure clauses are meant to uphold, not alter, original obligations – even in unexpected circumstances. The case serves as a reminder for businesses to define alternative options explicitly within their contracts if flexibility is desired.

Read More »

NEGLIGENCE – MEDICAL NEGLIGENCE – HOSPITAL ACCOUNTABILITY REINFORCED: COURT UPHOLDS NON-DELEGABLE DUTY IN MEDICAL NEGLIGENCE

In a landmark ruling, the court reinforced the hospital’s non-delegable duty of care, holding that even when services are outsourced to independent contractors, the hospital remains accountable for patient welfare. This decision emphasizes that vulnerable patients, reliant on medical institutions, must be safeguarded against harm caused by third-party providers. The ruling ultimately rejected the hospital’s defense of independence for contracted consultants, underscoring a high standard of duty owed to patients.

Read More »

CONTRACTS – CONTRACT FOR THE SALE OF GOODS FOB – REMOTENESS OF DAMAGES IN BACK-TO-BACK CONTRACTS – COURT DEFINES LIMITS ON LIABILITY

In a complex dispute involving back-to-back contracts, the court clarified the boundaries for assessing damages, emphasizing that a chain of contracts does not automatically ensure liability passes through. Although substantial losses resulted from delays and disruption, the court highlighted the importance of the remoteness of damages, noting that each contract’s unique terms ultimately limited liability. This decision emphasise the need for parties in chain contracts to carefully define indemnity and liability provisions, as damages are assessed based on foreseeability rather than simply the structure of linked agreements.

Read More »

TORT – BREAKING CONFIDENTIALITY – COURT CRACKS DOWN ON INSIDER LEAKS AND CORPORATE CONSPIRACY

In a recent ruling on corporate confidentiality, the court held two former employees liable for disclosing sensitive business information to a competitor, deeming it a breach of both employment contracts and fiduciary duties. This case highlights the serious consequences of unauthorized sharing of proprietary data and reinforces that such disclosures can lead to substantial legal and financial repercussions, even for the receiving parties if they knowingly benefit from confidential information.

Read More »
zh_TWZH
× 联系我们